企业拟开展环评审批、自主竣工验收和取得排污许可证,是否有先后顺序?应当按照什么顺序进行?

来源:上海嘉定 日期:2023年11月17日 22:10:36 文字 【 】【增加行距】【缩小行距】【加粗】【高亮】【还原 浏览:

企业环保知识问答(中英文对照版)

企业拟开展环评审批、自主竣工验收和取得排污许可证,是否有先后顺序?应当按照什么顺序进行?

Is there an order in which enterprises should carry out between environmental impact assessment approval, independent completion acceptance, and obtain Pollutant Discharge Permits? In what order should it be carried out?

建设单位应该在开工建设前完成环评的审批,通过环评审批后,方可开工建设。建设项目竣工后,即可开展自主竣工验收的工作,但是须在投入调试或生产前取得排污许可证。

Answer: The construction unit should complete the examination and approval of the environmental impact assessment before starting construction. The independent completion and acceptance work can be carried out after the completion of the construction project. The Pollutant Discharge Permit must be obtained before commissioning or production.


来源:嘉定环境,编辑:李莹燕